EDUCATIONAL QUALIFICATION\r\n\r\nB-Tech Mechanical Engineering.\r\nDr. M.G.R Educational & Research Institute, Chennai-600095, India.\r\nCGPA: 7.31\r\nYear: 2003 – 2007\r\n\r\n\r\n\r\n\r\nTECHNICAL QUALIFICATIONS\r\n\r\nCSWIP 3.4U Underwater Inspection Controller\r\nCSWIP Customer No. : 85118.\r\nDate of Issue : 17 April 2014.\r\nDate of Expiry : 13 December 2018.\r\n\r\nCSWIP 3.1 Certified Welding Inspector\r\nCSWIP Certificate No. : 35347/2 (Renewed).\r\nDate of Issue : 06 Oct 2008 & 24 July 2013 (Renewed).\r\nDate of Expiry : 20 August 2018.\r\n\r\nBGAS Painting Inspector Grade 2\r\nBGAS Certificate No. : 99557.\r\nDate of Issue : 14 July 2015.\r\nDate of Expiry : 04 Jun 2020.\r\n\r\nIRCA Certified ISO 9001:2015 QMS Lead Auditor\r\nCertificate No. : TVEQ0316439.\r\nIRCA Course No. : A17980.\r\nCourse Dates : 16th Feb - 20th Feb 2016.\r\n\r\nASNT LEVEL II\r\n• Radiographic Testing.\r\n• Ultrasonic Testing.\r\n• Magnetic Particle Testing.\r\n• Penetrant Testing.\r\n\r\nT-BOSIET and H2S CERTIFICATIONS BY OPITO\r\nCertificate No. : 52515501101115188863\r\nDate of Issue : November 2015.\r\nDate of Expiry : November 2019.\r\n\r\nSTCW-95 CERTIFICATIONS for the sea-farers in;\r\n• Personal Safety and Social Responsibility (PSSR).\r\n• Personal Survival Techniques (PST).\r\n• Elementary First Aid (EFA).\r\n• Fire Prevention and Fire Fighting (FPFF).\r\n• Helicopter Underwater Escape Technique (HUET).\r\n
EMPLOYMENT HISTORY:\r\n\r\nBUREAU VERITAS \r\n\r\nAbu Dhabi, UAE.\r\n\r\nPERIOD : Oct 2015 to Present.\r\nPOSITION : Client Representative / TPA (Offshore)\r\n\r\nWorked in the following projects as Third Party Multi-Discipline Inspection Engineer / ADMA-OPCO Client Representative for the following Offshore Projects\r\n\r\nUMM LULU FULL FIELD DEVELOPMENT PROJECT (Package -1)\r\n\r\nPosition : Client Representative / TPA\r\nProject No. : 2207 \r\nEPC Contractor : NPCC\r\n\r\nWorked as third party welding inspector in onshore at the NPCC Yard for the fabrication of jackets and decks. Worked as onboard ADMA-OPCO QA/QC representative for the installation of WHT-1 & WHT-3 Topside / Deck in the Umm Lulu Field. The installation barge was DLS-4200.\r\n\r\n\r\nNASR FULL FIELD DEVELOPMENT PROJECT (FFD Package -1)\r\n\r\nPosition : Client Representative / TPA\r\nProject No. : 3291 \r\nEPC Contractor : NPCC\r\n\r\nWorked as onboard ADMA-OPCO QA/QC Representative for the installation of WHT-4, WHT-5, WHT-6, WHT-7, WHT-8 and WHT-9 jackets in the NASR Field. The installation barge was DLS-4200. \r\n\r\n\r\nBU HASEER FIELD DEVELOPMENT PROJECT EARLY PRODUCTION SCHEME\r\n\r\nPosition : Client Representative / TPA\r\nProject No. : 5231 \r\nEPC Contractor : NPCC\r\n\r\nWorked as onboard ADMA-OPCO QA/QC representative for the installation of WHT BH-1 Jacket, Boat Landing, Conductor Protector and Riser Protector for BU-HASEER FFD (EPS). The installation barge was DLS-4200.\r\n\r\n\r\nUMM LULU FULL FIELD DEVELOPMENT PROJECT (Package -2)\r\n\r\nPosition : Client Representative / TPA\r\nProject No. : 2208 \r\nEPC Contractor : NPCC\r\n\r\nWorked as onboard ADMA-OPCO QA/QC representative for the installation of eight legged ULAP Jacket (Accomodation Platform) six legged ULSP Jacket (Separation Platform) and six legged ULUTP Jacket (Utilities Platform) in the Umm Lulu Field. The installation barge was DLS-4200.\r\n\r\n\r\n4 NEW GAS INJECTORS (4GI); 3 BARREN TOWERS (3BT); ZADCO UZ 750K WP-3A\r\n\r\nPosition : Client Representative / TPA\r\nProject No. : 167188 \r\nEPC Contractor : McDermott\r\n\r\nWorked as onboard ADMA-OPCO QA/QC Representative for the demolition of existing decks / Barren towers and installation of new decks for the ZK153/61 and ZK114.5/74.5 well head towers in the ADMA-OPCO Zakum fields. The installation barge was Derrick Barge-32 (DB-32) and the Hook-up barge was GMS-SCIROCCO.\r\n\r\n\r\n\r\nTRADING & AGENCY SERVICES (TRAGS)\r\nDoha, Qatar.\r\n\r\n\r\nPERIOD : June 2012 to Sept 2015.\r\nPOSITION : QA/QC Inspection Engineer\r\n\r\nWorked in the following projects at both onshore and offshore locations;\r\n\r\nFLOW ASSURANCE PROJECT (FAP)\r\n\r\n• Location - RASGAS & QATARGAS Offshore Fields.\r\n• Client - HHI / RASGAS / QATARGAS.\r\n• Contract - HHI-Q5CO-FAP-SUBSEA.\r\n\r\nEPC SERVICES FOR REPLACEMENT OF FUEL GAS / MIXED REFRIGERANT EXCHANGERS.\r\n\r\n• Location - Qatar Gas (Train-2 Shut Down)\r\n• Client - Qatar Gas.\r\n• Contract - LTC/C/VEN/1558/14.\r\n\r\nPROVISION OF EPC SERVICES FOR THREE COMBINED PROJECTS.\r\n\r\n• Location - Qatar Gas (Train-2 Shut Down)\r\n• Client - Qatar Gas.\r\n• Contract - LTC/VEN/1571/ 14.\r\n\r\nREPAIR & REFURBISHMENT OF PIPE SUPPORTS IN PS2, PS3 and WELL HEAD JACKETS OF MM & BH FIELDS\r\n\r\n• Location - QP Offshore (PS2, PS3, MM & BH Fields)\r\n• Client - Qatar Petroleum.\r\n• Contract - GC 10109800.\r\n\r\nEPIC for fire water system at PS2 and PS3 Offshore Platforms.\r\n\r\n• Location - QP Offshore (PS-3)\r\n• Client - Qatar Petroleum.\r\n• Contract - GC 12101900.\r\n\r\nTHREE COMBINED PROJECTS (Shut Down)\r\n\r\n• Location - Qatar Gas (QG 3&4; Train 7) \r\n• Client - Qatar Gas.\r\n• Contract - LTC-VEN-2132-13C57\r\n\r\n\r\n\r\nDESCON ENGINEERING\r\nDAS Island, Abu Dhabi, U.A.E\r\n\r\nPERIOD : Feb 2012 to May 2012.\r\nPOSITION : QA/QC Engineer\r\n\r\nWorked as QC Inspector for Welding and Piping for the ADGAS Shutdown for the 2012 Train-2 Overhaul in Abu Dhabi DAS Island. Responsible for the shutdown activities covering under variable scope (Piping) in the sulphur regeneration plant (Plant 7, Area 5) in Train 2 of the ADGAS LNG Plant.\r\n\r\n\r\n\r\n\r\n\r\nCARLTON INDUSTRIAL ENGINEERS.\r\nMumbai, India.\r\n\r\nPERIOD : Oct 2010 to Jan 2012.\r\nPOSITION : QA/QC Engineer\r\n\r\nWorked as QA/QC Engineer for the various offshore maintenance projects under ONGC.\r\n\r\nProject Summary:\r\n• Construction & Replacement of Heavy structures like “Burner Boom”.\r\n• Construction and Repairs of Piping, Mechanical Structures and Chemical Equipment.\r\n\r\nAlso responsible for the various piping & fabrication activities in onshore and offshore that includes incoming material inspection, Fit-up and Weld Visual inspections, NDT, RT Film Interpretation, Pressure testing, Blasting and Painting activities and dossier preparation.\r\n\r\n\r\n\r\n\r\n\r\nGULF PETROCHEMICAL SERVICES & TRADING LLC.\r\nSultanate of Oman.\r\n\r\nPERIOD : March 2008 to Sept 2010.\r\nPOSITION : QA/QC Engineer\r\n\r\nWorked in the following projects;\r\n\r\nMARMUL CENTRAL DEVELOPMENT (MCD) PHASE - III \r\n\r\n• Project - Marmul Central Development Phase - III\r\n• Client - Petroleum Development Oman\r\n• Contract - C 31 / 0875\r\n\r\nMCD PHASE - III – 24” & 36”PIPELINES\r\n\r\n• Project - Marmul Central Development Phase - III\r\n• Client - Petroleum Development Oman\r\n• Contract - C 31 / 0875\r\n\r\nMARMUL – AL KHALATA REPLACEMENT PIPELINE PROJECT\r\n\r\n• Project - Marmul – Al Khalata Replacement Pipeline Project\r\n• Client - Petroleum Development Oman\r\n• Contract - C 31 / 0799 VTC\r\n\r\nMAURID - MMPS PIPELINES:\r\n\r\n• Project - Maurid – MMPS Pipelines.\r\n• Client - Petroleum Development Oman\r\n• Contract - C 31 / 0799\r\n\r\n\r\n\r\n\r\n\r\n\r\nDas Offshore Engineering Pvt. Ltd.\r\nMumbai, INDIA\r\n\r\nPERIOD : June 2007 to Dec 2007\r\nPOSITION : QA/QC Engineer\r\n\r\nResponsible for the various piping & fabrication activities in the fabrication shop that includes incoming material inspection, Fit-up and Weld Visual inspections, NDT, RT Film Interpretation, Pressure testing, Blasting and Painting activities and dossier preparation.\r\n
Qualifications
B-Tech. Mechanical Engineering.
Dr. M.G.R Educational & Research Institute, Chennai 600095,India
CGPA : 7.31
Year: 2003 – 2007
CSWIP 3.4U Underwater Inspection Controller.
CSWIP Customer No. – 85118.
Date of Issue – 17 April 2014.
Date of Expiry – 13 December 2018.
CSWIP 3.1 Certified Welding Inspector.
CSWIP Certificate No. – 35347/2 (Renewed).
Date of Issue – 06 Oct 2008 & 24 July 2013 (Renewed).
Date of Expiry – 20 August 2018.
ASNT LEVEL II
• Radiographic Testing.
• Ultrasonic Testing.
• Magnetic Particle Testing.
• Penetrant Testing.
STCW-95 CERTIFICATIONS for the sea-farers in;
• Personal Safety and Social Responsibility (PSSR).
• Personal Survival Techniques (PST).
• Elementary First Aid (EFA).
• Fire Prevention and Fire Fighting (FPFF).
• Helicopter Underwater Escape Technique (HUET).
CERTIFICATIONS from VENTURE GULF TRAINING CENTRE, DOHA for
• H2S / BA AWARENESS.
• H.U.E.T & SEA SURVIVAL.
Career Summary
TRADING & AGENCY SERVICES (TRAGS)
Doha, QATAR.
Designation : Inspection Engineer
Period : June 2012 to Till Now.
Worked in the following projects;
REPAIR & REFURBISHMENT OF PIPE SUPPORTS IN PS2, PS3 and
WELL HEAD JACKETS OF MM & BH FIELDS
• Location – QP Offshore (PS2, PS3, MM & BH Fields)
• Period – Dec 2014 to Till Now.
• Client – Qatar Petroleum.
• Contract – GC 10109800.
Subsea Flow Assurance Project (FAP Project).
• Location – QG & RG Offshore fields
• Period – Sept 2014 to Dec 2014.
• Client – Qatargas / Rasgas.
EPIC for fire water system at PS2 and PS3 Offshore Platforms.
• Location – QP Offshore (PS-3)
• Period – October 2013 to Sept. 2014.
• Client – Qatar Petroleum.
• Contract – GC 12101900.
THREE COMBINED PROJECTS (Shut Down)
• Location – Qatar Gas (QG 3&4; Train 7)
• Period – July 2013 to October 2013; & Mar 2014.
• Client – Qatar Gas.
• Contract – LTC-VEN-2132-13C57
REPAIR & REFURBISHMENT OF PIPE SUPPORTS IN PS2, PS3 and WELL HEAD JACKETS OF MM & BH FIELDS (SHUT DOWN SCOPE)
• Location – QP Offshore (PS2, PS3, MM & BH Fields)
• Period – April 2013 to June 2013.
• Client – Qatar Petroleum.
• Contract – GC 10109800
The project scope is to carry out Corrosion survey at PS2 & PS3 Platform and Well Head Jackets of MM & BH Fields during 2013 shut-down at QP Offshore to determine inter-face corrosion at pipe support locations and to carry out repair / replacement of the supports / structure / pipe as per the project scope.
REPAIR & REFURBISHMENT OF PIPE SUPPORTS IN PS2, PS3 and WELL HEAD JACKETS OF MM & BH FIELDS
• Location – QP Offshore (PS2, PS3, MM & BH Fields)
• Period – July 2012 to April 2013.
• Client – Qatar Petroleum.
• Contract – GC 10109800.
The project scope is to carry out visual inspection and UT thickness survey at PS2 & PS3 Platform and Well Head Jackets of MM & BH Fields at QP Offshore to determine inter-face corrosion at pipe support locations and to carry out repair / replacement of the supports / structure / pipe wherever required or recommended by the client.
DESCON ENGINEERING
DAS Island, Abu Dhabi, U.A.E
Designation : QA/QC Inspector (Welding & Piping).
Period : Feb 2012 to May 2012.
Worked as QC Inspector for Welding and Piping for the ADGAS – DESCON Shutdown for the 2012 Train-2 Overhaul in Abudhabi DAS island.
Responsible for the shut down activities covering under variable scope (Piping) in the sulphur regeneration plant (Plant 7, Area 5) in Train 2 of the ADGAS LNG Plant.
CARLTON INDUSTRIAL ENGINEERS.
Mumbai, India.
Designation : QA/QC Engineer.
Period : Oct 2010 to Jan 2012.
Worked as QA/QC Engineer for the various offshore projects under ONGC.
Project Summary:
• Construction & Replacement of Heavy structures like “Burner Boom”.
• Construction and Repairs of Piping, Mechanical Structures and Chemical Equipments.
Gulf Petrochemical Services & Trading LLC.
Sultanate of Oman.
Designation : Inspection Engineer
Period : March 2008 to Sept 2010
Worked in the following projects;
MARMUL CENTRAL DEVELOPMENT (MCD) PHASE – III
• Project – Marmul Central Development Phase – III
• Period – Sept 2009 to Sept 2010.
• Client – Petroleum Development Oman
• Contract – C 31 / 0875
Worked as QA / QC Engineer as well as WINPCS coordinator for the project and reports to QA Engineer as well as Project Manager.
MCD Phase III is an on-plot station project comprising the expansion of existing station MMPS. The main scope of the project includes installation of a bulk separator, three booster pumps, two heaters, two tanks and construction of various inch dia piping (36” to ½”). The materials came used are CS, LTCS, SS, Cu-Ni etc.
MCD PHASE – III – 24” & 36” PIPELINES
• Project – Marmul Central Development Phase – III
• Period – March 2009 to April 2010.
• Client – Petroleum Development Oman
• Contract – C 31 / 0875
Worked as QA / QC Engineer for the project.
24” MCD-III Pipeline is a CS water injection pipeline of grade ISO 3183-3 L415MCS from MMPS station to the DWD station. It is a 1.1KM long HDPE lined pipeline with 9mm wall thickness.
36” MCD-III Pipeline is a CS Gross Liquid Pipeline of grade ISO 3183-3 L415 MCS from the MM-G Station to MMPS. It is having a length of 4KM with 17.5mm wall thickness, and 20mm at the road crossings.
MARMUL – AL KHALATA REPLACEMENT PIPELINE PROJECT
• Project – Marmul – Al Khalata Replacement Pipeline Project
• Period – Nov 2008 to Aug 2009.
• Client – Petroleum Development Oman
• Contract – C 31 / 0799 VTC
Worked as QA / QC Engineer for the project.
Marmul – Al Khalata Replacement Pipeline Project comprises of construction of three
new GRE Pipelines New 2.24 KM, 16ӯ GRP 35 barg Bulk Liquid Pipeline from MM-B to MM-G Station, New 2.95 KM, 18ӯ GRP 35 barg Bulk Liquid Pipeline from MM-C to
MM-G Station, New 3.295 KM, 18”Ø GRP 35 barg Bulk Liquid Pipeline from MM-D to MMPS Station) and decommissioning of old 14” CS above ground flowlines.
MAURID – MMPS PIPELINES:
• Project – Maurid – MMPS Pipelines.
• Period – Mar 2008 to Oct 2008.
• Client – Petroleum Development Oman
• Contract – C 31 / 0799
Worked as QA / QC Engineer and NDT Coordinator for the project.
MAURID – MMPS PIPELINES is a project comprising of two pipelines (a 28.75KM long 16” GRE Bulk Liquid Pipeline from Maurid to MMPS station and a 32.105KM long PE Lined 12” CS Water Injection Pipeline from DWD to Maurid Headers). The GRE Pipes were supplied by FPI (Future Pipe Industries LLC) and the bonding technique was
used to join the pipes. The CS Pipeline was HDPE lined by sub-contractor STS (Special Technical Services LLC) by providing 49 break flange pits.
Das Offshore Engineering Pvt. Ltd.
Mumbai, INDIA
Designation : Mechanical Supervisor.
Period : June 2007 to Dec 2007.
Responsible for the various piping & fabrication activities in the workshop.
• Safety Training Observation Program (STOP) completed.
• H2S Awareness & Escape.
• Enhanced Site Supervision (E.S.S.W) completed.
• Fire Fighter.
Areas Of Interest
• Underwater Welding and NDT.
• Professional Diving & ROV Operations
• Oil and Gas, Exploration and Production
• Pipeline Engineering.
• Welding Technology.
• Non-Destructive Testing.
• Shut-Downs.
Fathers Name : P.N Narayanan Namboothiri.
Date of Birth : 5th July 1985.
Marital Status : Single
Nationality : Indian
Passport Number : G 6 0 6 8 3 5 3
Place of Issue : Cochin
Date of Issue : 19 – 11 – 2007
I hereby declare that the information furnished above is true & with best of my Knowledge & belief.
(NEERAJ NARAYANAN P.N.)
For further information on our international agency and available workers please contact us today (click here)
BackIf you are interested in new employment opportunities please register on our website (click here)
Back